Delays to Plant 'Could Cost Pounds 3m' ; Bill for Flagship Waste Recycling Centre Will Soar, Warns Developer
The Journal › January 11, 2007
Linked as:
The Journal › January 11, 2007
Linked as:Summary
A FLAGSHIP waste recycling centre for Northumberland could cost 25% extra to build because of a delay in securing planning permission, it was claimed yesterday.
SITA UK says local opposition means the bill for developing the pounds 11m waste recycling and transfer station at West Sleekburn, near Bedlington, could soar by between pounds 2m and pounds 3m.See the full content of this document
Extract
Delays to Plant 'Could Cost Pounds 3m' ; Bill for Flagship Waste Recycling Centre Will Soar, Warns Developer
The waste management company also claims the project could be delayed by a year after county councillors refused to grant plan...
See the full content of this document
Sponsored links
ver las páginas en versión mobile | web
ver las páginas en versión mobile | web
© Copyright 2012, vLex. All Rights Reserved.
Contents in vLex United Kingdom
Explore vLex
For Professionals
For Partners
Company
Other documents:
1 dress...3 looks | Qatar Financial Centre Top Legal Job for Lord Woolf | simple deal earned kewell's agent pounds 2m | Welcome Rebirth of the Advisers ; City Comment | Current developments in S corporations. | report issued on bradford island contamination in oregon | The Daily Dish ... | Likely v. Ruane, (1st Cir. 2011)